How Long Does A Laundry Renovation Take?

How long does a laundry renovation take?

A laundry renovation can take between 2-6 weeks, depending on the complexity and scope of the project. Generally, a larger laundry with an extensive renovation plan will take significantly longer than a renovation project focused on cosmetic changes.  

If you are planning a makeover for the laundry, here’s what you need to know about the expected timeline of the project.

 

Estimate Timeline for A Laundry Renovation

1. Design and planning

Every laundry renovation project starts with design. A renovation company like Venaso will measure and map out the current dimensions of the laundry to determine what is possible with the current layout, plumbing, and objectives of the project.

The design process is where homeowners will be most involved – you’ll be able to shape every aspect of the new laundry to your preferences, from layout to cabinetry and colours. Our laundry renovation designers will present the new design in 3D modelling software to provide a vision of the expected outcome. 

Depending on the scope and how many changes are required, it can take up to one week to achieve a finalised design for the laundry renovation project.

 

2. Permit application

A laundry renovation involves plumbing, electrical, and possibly structural work, all of which require a building permit from the local council in Perth. Contractors will usually apply for a council building permit on behalf of homeowners. 

Building permit approvals for certified laundry room renovations are typically issued within 10 business days.

 

3. Site preparation

Contractors may take 1-2 days to prepare the laundry room for renovation, including demolition work such as removing appliances, dismantling old cabinetry, and tearing down tiling and walls.

 

4. Plumbing and electrical work

Plumbing and electrical work are carried out in line with the new layout of the laundry room. Rough-ins for lighting, power points, and taps are completed, as well as the relocation of water and drainage pipes. The plumbing and electrical stage can take 2-4 days to complete. 

 

5. Tiling and cabinetry installation

Contractors begin installing new floor and wall tiling, brand-new cabinetry, and countertops in the laundry room. Installing these fixtures can take 3-5 days. 

Tiling installation can take longer for intricate patterns or large-format tiles, as extra care is required to ensure the correct spacing and prevent damage to the material.

 

6. Appliances and testing

Appliances are connected to the plumbing and set to run to check for any leaks. Contractors will also check the ventilation and drainage requirements of the space to ensure that excess moisture does not become trapped in the laundry (which can lead to mould growth). 

Appliance installation and testing will take 1-2 days.

 

7. Cleaning and inspection

Dust and debris are removed, and a final inspection is conducted to ensure that the renovation outcome aligns with the planned design. 

 

How long does a laundry renovation take?

 

Factors Affecting The Laundry Renovation Timeline

A laundry renovation is a significantly simpler undertaking compared to a bathroom or kitchen renovation, though it still has its complexities.

Changes to the laundry room size or location

Designs that relocate or enlarge the laundry room will involve structural modifications. Structural work can significantly extend the duration of the renovation and will require careful planning to ensure it is completed on time. Keep in mind that relocating the laundry to a different part of the home will usually involve additional structural compliance checks, which lead to extended timelines.

On the other hand, a laundry room that only involves cosmetic changes can be completed much quicker and will be less affected by unexpected issues, such as plumbing leaks or structural damage.

Availability of contractors

Renovation specialists work with plumbers and electricians to carry out the waterproofing and electrical work required for the renovation. Scheduling conflicts or unavailability may result in delays in the renovation project. Confirming a renovation schedule with a contractor early allows trade services to be booked weeks in advance, reducing the risk of encountering unavailability.

Choice of materials

Materials chosen for the renovation project are sourced early by the renovation specialist. However, unexpected supply chain issues can cause shortages in the chosen materials, resulting in delays. Experienced laundry room renovation specialists partner with reliable, local suppliers for tiles, appliances, and fittings to minimise delays and ensure a favourable outcome. 

 

At Venaso Selections, we offer premium-quality laundry renovations in Perth that cover the entire process from start to end. We have an in-house team of designers who work closely with you to develop a new laundry room that is both visually stunning and functional. We also partner with leading Australian suppliers like Adp, Abey, and Jamie J to offer high-quality fittings and fixtures for each laundry renovation project. Contact us to book a free consultation with our laundry renovation specialists, or visit our showrooms in Booragoon and Subiaco. [/vc_column_text][/vc_column][/vc_row]